Logistics hall, Dahlewitz

Transaction + Investment

Technical due diligence (TDD)

Credit Suisse Asset Management (Schweiz) AG was in the purchasing process for the logistics hall still under construction in Dahlewitz, around 15 minutes drive from Berlin-Brandenburg Airport. A technical due diligence was required to illustrate the status quo of the construction progress as well as to point out possible risks in the course of commissioning and handover.

Challenges

The property is a logistics hall, which was almost completed at the time of the investigation. One of the two tenants had already moved in. Accordingly, some of the technical facilities were already in operation. However, due to the conversions taking place in the second tenant area, there were still re-plannings at the tenant's request and the associated changed technical requirements. In regard to the construction progress and the changed tenant requirements, it was necessary to travel to the project several times and record the status quo.

Added value

We were able to point out the risks to the client and the expected costs. Our analysis had an influence on the negotiation talks in the course of the purchase.

Project data

  • Service area

    Transaction + Investment

  • Solution

    Technical due diligence

  • Client

    Credit Suisse Asset Management (Schweiz) AG

  • Project

    Logistics hall

  • Usable area

    18,400 sqm

  • Location

    Dahlewitz

  • Timeframe

    07/2021 to 12/2021

Ourprojects

Author: plan b

SDK Headquarters, Fellbach

Client representation GC construction supervision Real estate and location strategies

Read more …

What is your next step?

We look forward to talking about your next project

Contact us